Tue December 14, 2021 - West Edition #26 Seattle DOT
Seattle Mayor Jenny A. Durkan and the SDOT team celebrated the final phase of West Seattle Bridge repairs beginning and SDOT being on schedule to reopen the bridge at full strength next year.
"Since March 2020, our city has faced unprecedented challenges, including the closure of the West Seattle Bridge," said Mayor Durkan. "After the important work to stabilize the bridge then design the specialized repairs, SDOT is starting the final repair phase of the West Seattle Bridge. Because of the work at SDOT, the end is in sight to reopen the bridge in the coming months. This is an important milestone for our residents, commuters, and businesses as we urgently work to reconnect West Seattle to the greater region."
Construction crews have been diligently working to repair the West Seattle Bridge since it was closed in March 2020. Construction crews from Kraemer North America completed the first phase of stabilization repairs in 2020 and since then have completed the design to repair the bridge and selected the specialized contractor to complete the work. Now, construction crews are returning to the West Seattle Bridge to begin the final phase of the high-priority work to repair the bridge and prepare it for reopening next year. The project also will add epoxy and carbon fiber wrap to the Spokane Street Swing Bridge to fill any existing cracks and strengthen that bridge further.
The final phase of repairs includes:
SDOT and Kraemer North America agreed on a construction schedule that will complete repairs by mid-2022, pending any unforeseen issues due to extreme weather events, supply chain problems, worker shortages or other unexpected conditions.
Following Kraemer completing the repairs, SDOT will test the bridge for strength and resiliency before reopening it to traffic. SDOT will share a more specific reopening date — and community activities to celebrate it — as work advances.
Current costs for repairs remain consistent with previous estimates. The newly signed construction contract with Kraemer estimates that contractor costs for the final phase of repairs will be approximately $45 million. This phase is one part of the larger West Seattle Bridge Program, including all the work related to the West Seattle Bridge closure. It consists of both phases of repairs to high bridge, rehabilitation work on the low bridge and many other traffic and safety improvements built throughout West Seattle, Delridge, High Point, South Park and Georgetown to address detour traffic and provide mobility options.
Initial work includes hydroblasting to open access points for work platforms that will hang from the bridge and give workers access to the underside. Throughout December, crews will hoist the platforms into place and drill out concrete cores to add steel tendons to post-tension the bridge for extra strength.
"The emergency stabilization of the West Seattle Bridge that's already occurred gives these full repairs a head start and we all look forward to their completion next summer to restore this vital transportation link for tens of thousands of Seattle residents," said Seattle City Councilmember Alex Pedersen, chair of the council's transportation committee. "I'll continue to be a champion for investing in our infrastructure and strengthening Seattle's bridges and I am pleased the final phase of these repairs are underway so everyone can use the West Seattle Bridge again as soon as possible."
"We're nearing the finish line for our West Seattle and Duwamish Valley communities," said Community Task Force Co-chair Paulina López. "A priority of the Community Task Force has been to minimize the burden of the bridge closure on our most impacted communities. We appreciate that SDOT conducted inclusive processes in three neighborhoods to identify pedestrian improvements and traffic calming options to mitigate the impact of the closure. We are also appreciative that, through the priority hire program, some of the economic benefits of this major repair effort can stay within these communities."
Brosamer & Wall Utilize Unique Concrete On 130-Year-Old Canal
Tips for Minimizing Impact of Rising Fuel Prices
Beam Global, Volvo CE Announce Partnership to Offer Off-Grid EV Charging Systems With Volvo Electric Construction Equipment
Yanmar Compact Equipment Promotes Maintenance Kits for Convenient Servicing
$125M in Incentives for Off-Road Zero-Emission Equipment Available Through California's CORE Project
Tennessee Tech Budget Funding More Than $100M for New Building Projects
Lake City, S.C., Building New $10M Wastewater Treatment Facility
JLG Names Andy Daw Vice President, Global Procurement, Supply Chain
Construction Equipment Guide 470 Maryland Drive Fort Washington, PA 19034 800-523-2200
Construction Equipment Guide covers the nation with its four regional newspapers, offering construction and industry news and information along with new and used construction equipment for sale from dealers in your area. Now we extend those services and information to the internet. Making it as easy as possible to find the news and equipment that you need and want.
Contents Copyrighted 2022, by Construction Equipment Guide, which is a Registered Trademark, registered in the U.S. Patent Office. Registration number 0957323. All rights reserved, nothing may be reprinted or reproduced (including framing) in whole or part without written permission from the publisher. All editorial material, photographs, drawings, letters, and other material will be treated as unconditionally assigned for publication and copyright purposes and are subject to Construction Equipment Guide’s unrestricted right to edit and comment editorially. Contributor articles do not necessarily reflect the policy or opinions of this publication. Read our privacy policy here.